i have a new cluster in 6.7 with DVS

As i had a single physical switch, and the second take too long time to be delivered, i started to provision VMs on the cluster like that.

The second switch is now here.

What would the tasks’s workflow to detach and attach the link to the new switch ?



View Reddit by skewthordon86View Source

 

To see the full content, share this page by clicking one of the buttons below

Related Articles

One Comment

  1. 1. You bring up the new switch and cable it.

    2. You configure the necessary VLANs on the ESXi host ports.

    3. You configure the necessary VLANs on the uplink between the switches.

    4. You unplug one (of at least two – I hope) of the host ports from the first switch and plug into the second switch.